A 2,000 sqm commercial warehouse and office facility currently under construction.
A 2,000 sqm commercial warehouse and office facility currently under construction.
Full structural construction, roofing, MEP rough-in, office mezzanine, perimeter fencing.
Dec 01, 2025 — Dec 20, 2025
Jan 05, 2026 — Jan 25, 2026
Feb 01, 2026
Electrical and plumbing rough-in at 70% completion. Office mezzanine structural steel fabricated and installation underway.
Main roofing installation completed. Pre-cast exterior panels are being installed. MEP rough-in has begun on the ground floor.
Foundation works, footing, and ground floor structural steel erection have been completed. Ready for roofing installation.